15 Nov 2010 Official Opening of KTPH
28 Jun 2010 Opening of Acute and Emergency Care Centre (A&E) and Inpatient Wards
29 Mar 2010 Specialist Outpatient Clinics at KTPH fully operational
28 Mar 2010 Open House for KTPH Specialist Outpatient Clinics (SOC)
26 Jun 2009 Topping Out Ceremony
03 Apr 2008 Superstructure Commencement Ceremony
10 Jan 2008 Award of superstructure construction contract to Hyundai Engineering & Construction Co Ltd
20 April 2007 Tree Planting with MP & grassroots leaders
07 Oct 2007 Exhibition on "Healthy Community Up North" to showcase KTPH
28 Nov 2006 Ground Breaking Ceremony
10 Nov 2006 Award of basement and piling contract for KTPH to Singapore Piling & Civil Engineering Pte Ltd (SP)
04 May 2006 Award of Design Consultancy to CPG Consultants Pte Ltd in partnership with Hillier International for AH@Yishun project
23 Nov 2005 Adoption of Yishun Pond
27 Oct 2005 Award of project management services for AH@Yishun project
17 Mar 2004 Announcement in Parliament by Health Minister Mr Khaw Boon Wan about challenging the Alexandra Hospital (AH) team to rebuild AH and  move it to the north of Singapore